PREPARATION WORK FOR “THERMAL POWER PLANT V” PROJECT IS PROGRESSING

PREPARATION WORK FOR “THERMAL POWER PLANT V” PROJECT IS PROGRESSING

 

🇲🇳 Preparatory work for the “Thermal Power Plant V” project, aimed at balancing Ulaanbaatar’s rapidly growing energy demand and strengthening the reliability of the city’s infrastructure, is progressing steadily.

➡️ As of today, 142 geotechnical drilling holes have been completed at the project site. Construction of the foundation for the plant is scheduled to begin in April 2026.

✅ The plant will be constructed on the ash pond area of CHP-2 located in the 20th khoroo of Bayangol District. The project contractor is Mitime International, and the project is being implemented under a Public Private Partnership framework.

🌱 The plant will incorporate environmentally friendly technologies, including:

CFB (Circulating Fluidized Bed) boiler technology

Flue gas control systems to reduce NOx and SO₂ emissions

Air cooled condensers

Water recycling systems

🇲🇳The financing structure and investment sources of the project are being arranged and coordinated through the Capital Investment Fund, with implementation and management carried out by UBIM.

✅ Once completed, the project will become a major source of electricity and heat supporting residential development and urban expansion in the western and north-western areas of Ulaanbaatar.