CONSTRUCTION PROGRESS OF CHP-5 PROJECT REVIEWED

CONSTRUCTION PROGRESS OF CHP-5 PROJECT REVIEWED

 

🇲🇳✅ The management team of UBIM, together with representatives of Mitime International LLC and Ulaanbaatar Thermal Power Plant-5 LLC, held a progress review meeting on the construction of the Fifth Combined Heat and Power Plant (CHP-5) project.

➡️ The project’s overall completion was reported at 45%. Earthworks and foundation casting have been completed. Civil and construction works are 30% complete, the manufacturing and delivery of main equipment are 60% complete, and other equipment works are 40% complete.

❄️ Due to weather conditions, work at the construction site has been temporarily adjusted and is scheduled to resume in March 2027. The project teams discussed alignment of the work schedule, equipment manufacturing and delivery, and the next stages of implementation.

✅ Implemented under a public-private partnership, CHP-5 is designed to generate 300 MW of electricity and 340 Gcal/h of heat.

🇲🇳✅ The investment contribution to be borne by the Municipality is being financed through UBIM participates in the project’s financing structure through the Development Fund.