CAPITAL CITY EXECUTIVE BRIEFING HELD

CAPITAL CITY EXECUTIVE BRIEFING HELD

 

🇲🇳 The regular executive briefing of Ulaanbaatar city officials was held today, focusing on the progress of land acquisition activities and the key issues currently facing implementation.

➡️ Under subcenter development and ger area redevelopment programs:

✔️ Selbe Subcenter – 2,095 of 2,206 land parcels acquired

✔️ “Khanyn Material” Area – 210 of 213

✔️ Bayanburd – 65 of 85

✔️ “Ulaanbaatar Arena” Project – 8 of 15

➡️ Overall, 2,378 out of 2,519 land parcels under ongoing projects have been successfully cleared.

➡️ Within road and engineering infrastructure projects:

✔️ Tuul Expressway – 38 land parcels acquired

✔️ Tuul-1 Collector – 51 land parcels

✔️ Narnii Road East Extension (4 km) – 132 of 165

✔️ Sukhbaatar District, 23rd Khoroo (Orgil Project) – 53 of 59 land parcels

➡️ For social infrastructure developments:

✔️ Gandan Model Street Project – 36 households relocated

✔️ Waste-to-Energy Plant – 121 of 158 land parcels

✔️ Fire and Rescue Station Project – 34 of 41 land parcels acquired

🇲🇳✅ In 2026, land acquisition is planned for 8,664 land parcels across 153 projects, including:

✔️ 9 redevelopment projects – 1,493 parcels

✔️ 68 road and engineering infrastructure projects – 5,674 parcels

including 3,029 parcels for the Ring Road project

✔️ 76 social infrastructure projects – 1,497 parcels

⚠️ Key challenges include:

•Legal enforcement and budget/financing constraints

•Land and property related court disputes

•Compulsory acquisition processes

•Need to accelerate implementation

➡️ It was also emphasized that an integrated system and monitoring dashboard should be introduced to enhance transparency and efficiency of land acquisition activities.